Sammamish Issaquah-Fall City Road Improvement 12/13/19 Update
Subscribe to blog
PROJECT UPDATE
*revised 12/11/19
- Project Three Week Look-Ahead:
- UPDATE: Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
- Using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times during periods of peak delay
- Clear NE corner of Klahanie Dr SE and IFCR
- Continue work on PCMS pond
- Remove large KLAHANIE signs on the NW and NE corners of Klahanie Dr SE and IFCR (Replacement signs will be designed and installed by the Klahanie Homeowners Assoc)
- Remove the Pacific Cascade Middle School (PCMS) Sign. A replacement design and location will be coordinated directly with PCMS and ISD. Thank you!
- UPDATE: Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
- Detour Route Map link (includes mitigation measure locations)
Note: Road Construction Hours
- Monday - Friday 9:30 am - 3:30 pm
- During road closure M-F 7 am - 8 pm (between 247th and Klahanie Dr)
- Optional Saturday work 9 am - 6 pm
Stay tuned for more updates